| Manager |
Project |
|
Project Title |
|
Estimated Budget |
Project Phase |
| CRAIG PETERSON |
| |
M2446 |
|
5TH & KIRKHAM CHILD CARE CENTER |
|
$6,724,000.00 |
Construction |
| |
M5405 |
|
654 MINNESOTA CAMPUS DATA CENTER TENANT IMPROVEMENTS |
|
$4,450,000.00 |
Substantial Completion |
| |
M7446 |
|
KIRKHAM CHILDCARE PLAY YARD EXTENSION |
|
$300,000.00 |
Construction |
| |
M7477 |
|
WILLIAM J. RUTTER BLDG (MBCC) ABOVE CEILING MECHANICAL EQUIPMENT ACCESS |
|
$100,000.00 |
Construction Documents |
| |
M8443 |
|
LHTS ANNEX RENOVATION |
|
$5,000,000.00 |
Design/Engineer Selection |
| |
M8454 |
|
1482 5TH AVENUE HOUSING REMODEL |
|
$167,000.00 |
Warranty |
| |
M9406 |
|
SFGH BLDG 1 ROOM 152 DEPT OF MED WOOD STOVE |
|
$80,000.00 |
Design Development |
| DAN KRASNOW |
| |
M3444C |
|
IRM 600 T CHILLER |
|
$3,000,000.00 |
Construction |
| |
M6424 |
|
HSE HIGH VOLTAGE SWITCHGEAR REPLACEMENT |
|
$3,227,435.00 |
Construction |
| |
M7410A |
|
PARNASSUS INFRASTRUCTURE - CONDENSATE RETURN SYSTEM BYPASS RENEWAL |
|
$1,237,774.00 |
Warranty |
| |
M7410B |
|
MSB CHILLER LOOP BYPASS PIPING RENEWAL |
|
$552,176.00 |
Warranty |
| |
M7410C |
|
HSIR INDUSTRIAL HOT WATER SYSTEM RENEWAL |
|
$422,377.00 |
Warranty |
| |
M7410D |
|
MU H-LEVEL DETERIORATED WATER PIPING REPLACEMENT |
|
$278,530.00 |
Owner Move-In |
| |
M7410E |
|
MSB MACHINE ROOM S186 SEWER PIPING REPLACEMENT & CONTAINMENT WALL RENEWAL |
|
$400,000.00 |
Warranty |
| |
M7414A |
|
MCB DEAERATOR (DA) TANK AND PIPING REPLACEMENT |
|
$250,000.00 |
Warranty |
| |
M7416A |
|
MCB FAN AND MOTOR REPLACEMENT |
|
$420,000.00 |
Warranty |
| |
M7450 |
|
ALDEA SAN MIGUEL COMMUNITY CENTER |
|
$1,600,000.00 |
Construction Documents |
| |
M7482 |
|
09-10 STATE RENEWAL PLANNING ESTIMATES |
|
$25,000.00 |
Design/Engineer Selection |
| |
M8405 |
|
PCUP AQUEOUS-AMMONIA CARRIER PIPE RENEWAL |
|
$796,382.00 |
Warranty |
| |
M8435 |
|
SON HEAT EXCHANGE & PUMP REPLACEMENT |
|
$60,000.00 |
Design/Engineer Selection |
| |
M8439 |
|
INSTITUTE FOR REGENERATION MEDICINE BUILDING ANCILLARY SITEWORK |
|
$4,544,000.00 |
Construction |
| |
M8450 |
|
PARNASSUS STAIRWELL LIGHT FIXTURE REPLACEMENT |
|
$117,485.00 |
Construction |
| |
M8450A |
|
MSB STAIRWELL LIGHT FIXTURE REPLACEMENT |
|
$123,383.00 |
Construction |
| |
M8450B |
|
HSIR-WEST STAIRWELL LIGHT FIXTURE REPLACEMENT |
|
$123,383.00 |
Construction |
| |
M8450C |
|
HSIR EAST STAIRWELL LIGHT FIXTURE REPLACEMENT |
|
$123,383.00 |
Construction |
| |
M8450D |
|
SON STAIRWELL LIGHT FIXTURE REPLACEMENT |
|
$123,383.00 |
Construction |
| |
M8451 |
|
MCB STAIRWELL LIGHT FIXTURE REPLACEMENT |
|
$42,219.00 |
Construction |
| |
M8452 |
|
LAUREL HEIGHTS STAIRWELL LIGHT FIXTURE REPLACEMENT |
|
$21,287.00 |
Construction |
| |
M8457 |
|
MSB S16 THRU S24 EMERGENCY RELOCATION AND FACILITY RESTORATION |
|
$50,000.00 |
Construction |
| |
M9405 |
|
GENENTECH HALL MONITORING BASED COMMISSIONING (MBCx) |
|
$1,100,000.00 |
Design/Engineer Selection |
| |
M9408 |
|
BYERS HALL MONITORING BASED COMMISSIONING (MBCx) |
|
$1,200,000.00 |
Design/Engineer Selection |
| |
M9425 |
|
PARNASSUS INFRASTRUCTURE UTILITY METER REPLACEMENTS |
|
$1,500,000.00 |
Design/Engineer Selection |
| |
M9426 |
|
PARNASSUS INFRASTRUCTURE AIR COMPRESSOR REPLACEMENT & PUMP MOTOR VFD'S |
|
$1,000,000.00 |
Design/Engineer Selection |
| |
M9427 |
|
MSB LARC DOOR & FRAME REPLACEMENTS |
|
$700,000.00 |
Design/Engineer Selection |
| |
M9428 |
|
HSIR FAN & DAMPER REPLACEMENTS |
|
$725,000.00 |
Design/Engineer Selection |
| |
M9429 |
|
MSB/CSB/HSIR FIRE DOOR REPLACEMENTS |
|
$1,000,000.00 |
Design/Engineer Selection |
| |
M9430 |
|
KORET VISION RESEARCH ENERGY MANAGEMENT CENTER SYSTEM RENEWAL |
|
$600,000.00 |
Design/Engineer Selection |
| |
M9431 |
|
HUNTER POINT'S LOW PRESSURE STEAM BOILER SYSTEM REPLACEMENT |
|
$500,000.00 |
Design/Engineer Selection |
| |
M9432 |
|
KORET VISION RESEARCH FIRE ALARM PANEL AND CPU REPLACEMENT |
|
$140,000.00 |
Design/Engineer Selection |
| |
M9433 |
|
MSB BASEMENT FIRE SPRINKLER VALVE REPLACEMENT |
|
$20,000.00 |
Design/Engineer Selection |
| DENISE STRIPLING |
| |
M6418 |
|
PARNASSUS UTILITIES MASTER PLAN |
|
$2,436,000.00 |
Ad/Bid |
| |
M7485 |
|
CLS UCSF NETWORK ACCESS PROJECT |
|
$500,000.00 |
Schematics |
| |
M8414 |
|
SFGH MAIN HOSPITAL UPGRADE TOILET ROOM 1X59 - ADA ACCESSIBLE |
|
$80,000.00 |
Construction |
| |
M8418 |
|
GH S128-A NANOFABRICATION CLEAN ROOM |
|
$100,000.00 |
Construction |
| |
M8434 |
|
PCUP MODICON CONTROL SYSTEM REPLACEMENT |
|
$390,000.00 |
OSHPD |
| |
M8444 |
|
CAMPUS WIDE PUBLIC SAFETY - ELECTRONIC DISPLAY BOARD SCOPE |
|
$5,000.00 |
Programming |
| |
M9434 |
|
MISSION BAY HOUSING RETAIL CLS TENANT IMPROVEMENTS |
|
$16,000.00 |
Design/Engineer Selection |
| DON SZETO |
| |
M7451 |
|
LUCIA CHILD CARE CENTER RENOVATION |
|
$885,000.00 |
Construction Documents |
| |
M7480 |
|
MCB 2ND FLR PEDIATRICS NEUROPATHOLOGY LAB RENOVATION |
|
$260,000.00 |
Construction |
| |
M8403 |
|
MCB 3RD FLOOR OAAIS & STUDENT ACCOUNTS |
|
$1,615,500.00 |
Construction |
| |
M9401 |
|
ACC/MU GARAGE AND ACC TOWER CONCRETE SPALLS ASSESSMENT |
|
$112,000.00 |
Programming |
| |
M9411 |
|
OYSTER PT - CLS MAIL OFFICE RENOVATION & STANDBY GENERATOR INSTALLATION |
|
$350,000.00 |
Programming |
| EILEEN JUE |
| |
M4417 |
|
MB BLDG 24C QB3 EQUIPMENT |
|
$2,160,000.00 |
Owner Move-In |
| |
M4417A |
|
MB BLDG 24C QB3 USER MODIFICATIONS / GROUP 2 & 3 BUDGET |
|
$4,535,000.00 |
Construction Documents |
| |
M4418 |
|
MB BLDG 24C QB3 RELOCATION |
|
$800,000.00 |
Owner Move-In |
| |
M6405 |
|
MISSION BAY CAMPUS - PHOTOVOLTAIC SYSTEM |
|
$900,000.00 |
Construction Documents |
| |
M7407 |
|
MB BLDG 23B PUBLIC RESTROOMS |
|
$250,000.00 |
Construction Documents |
| |
M7408 |
|
MISSION BAY 21A PARKING STRUCTURE - BANNERS |
|
$33,468.00 |
Construction |
| |
M8409 |
|
MILLBERRY UNION I LEVEL RM 005 REMODEL |
|
$50,000.00 |
Design/Engineer Selection |
| |
M9417 |
|
HSE 5TH FLOOR RM 503/595 LAB TO OFFICE RENOVATION |
|
$190,000.00 |
Design/Engineer Selection |
| FRANK FASANO |
| |
M7412A |
|
HSIR FIRE ALARM SYSTEM RENEWAL |
|
$350,000.00 |
Construction Documents |
| |
M7412B |
|
MSB FIRE ALARM SYSTEM RENEWAL |
|
$250,000.00 |
Construction Documents |
| |
M9420 |
|
SCHOOL OF NURSING-FIRE ALARM REPLACEMENT |
|
$228,000.00 |
Design/Engineer Selection |
| |
M9421 |
|
SCHOOL OF DENTISTRY-FIRE ALARM REPLACEMENT |
|
$404,000.00 |
Design/Engineer Selection |
| |
M9422 |
|
PCUP-FIRE ALARM REPLACEMENT |
|
$120,000.00 |
Design/Engineer Selection |
| |
M9423 |
|
CLINICAL SCIENCES-FIRE ALARM REPLACEMENT |
|
$288,000.00 |
Design/Engineer Selection |
| |
M9424 |
|
KORET FIRE ALARM REPLACEMENT |
|
$140,000.00 |
Design/Engineer Selection |
| GARY NELSON |
| |
M5444 |
|
MISSION BAY CAMPUS 2ND MPOE/MDF (ENS) |
|
$6,164,472.00 |
Reviews EH&S/FM Utilities/ENS |
| |
M5462 |
|
MBAY 23B POLICE SUB-STATION |
|
$1,809,422.00 |
Programming |
| |
M6450 |
|
654 MINNESOTA BUILDING-WIDE INFRASTRUCTURAL IMPROVEMENTS |
|
$4,900,000.00 |
Construction |
| |
M6450A |
|
654 MINNESOTA BUILDING-ADDITIONAL SCOPE |
|
$20,000.00 |
Warranty |
| |
M8417 |
|
HSIR SEISMIC STUDY |
|
$500,000.00 |
Programming |
| JULIE GALLIVAN |
| |
M3444D |
|
IRM OEH&S AND TRAILHEAD ACCESS STAIRS |
|
$150,000.00 |
Design/Engineer Selection |
| |
M7411A |
|
HSIR UTILITY TUNNEL MOTOR CONTROL CENTER EMERGENCY ELECTR PANEL REPLACEMENT |
|
$128,000.00 |
Construction |
| |
M7411B |
|
CSB 7TH FLOOR ELECTRICAL PANEL "B" AND FRP ROOFTOP PANEL REPLACEMENT |
|
$305,000.00 |
Construction |
| |
M7434 |
|
ALDEA STUDENT HOUSING REHABILITATION |
|
$5,100,000.00 |
Construction |
| |
M7489 |
|
PARNASSUS CENTRAL RECEIVING AREA SECURITY GATE |
|
$80,000.00 |
Construction Documents |
| |
M8411 |
|
SOD LOBBY AREA REDESIGN |
|
$870,766.00 |
Construction Documents |
| LUANNE MULLIN |
| |
M5470 |
|
HSW 14TH FLOOR DEPT OF OB/GYN LAB RENOVATION |
|
$4,985,068.00 |
Owner Move-In |
| |
M6409 |
|
HSW 7TH FLOOR NEUROLOGICAL SURGERY LAB RENOVATION |
|
$794,062.00 |
Ad/Bid |
| |
M6428 |
|
MSB 13TH FLR, S1372 ANATOMY DEPT RENOVATION |
|
$7,500,000.00 |
Design Development |
| |
M6462 |
|
MSB 11TH FLR S/M ORTHO SURGERY LAB/OFFICE RENOVATION |
|
$4,435,078.00 |
Construction Documents |
| |
M6464 |
|
MSB 5TH FLOOR S/M LAB MED RENOVATION |
|
$2,000,000.00 |
Construction |
| |
M7415 |
|
DEFERRED MAINT 06-07, BP 6 - KALMANOVITZ LIBRARY ELEVATOR CONTROLS RENEWAL |
|
$1,000,000.00 |
Construction |
| |
M7424 |
|
HSE 4TH FLOOR ROOMS 447-448 S/M REMODEL |
|
$434,181.00 |
Warranty |
| MIKE TOPORKOFF |
| |
M3444 |
|
INSTITUTE FOR REGENERATION MEDICINE BUILDING |
|
$123,256,000.00 |
Construction Documents |
| |
M3444A |
|
IRM GROUP 2 & 3 EQUIPMENT, FURNITURE AND RELOCATION |
|
$3,810,000.00 |
Schematics |
| |
M7404 |
|
CSB SEISMIC INTERIM MITIGATION STUDY, PHASE 1 - CONCEPTUAL DESIGN/ESTIMATE |
|
$100,000.00 |
Programming |
| PATRICK MCGEE |
| |
M4443 |
|
SFGH NGMAN BUILDING FACILITIES UPGRADE |
|
$1,198,087.00 |
Construction |
| |
M7401 |
|
HSE 15 S/D CRANIOFACIAL & MESENCHYMAL BIOLOGY PROGRAM LAB RENOVATION |
|
$6,992,239.00 |
Construction |
| |
M7464 |
|
SOD D4203 DENTAL LAB RENOVATION |
|
$633,138.00 |
Owner Move-In |
| PATTI MITCHELL |
| |
M5417 |
|
HSE 5 CENTER FOR BIOENGINEERING AND TISSUE REGENERATION |
|
$3,934,653.00 |
Contract Award |
| |
M7402 |
|
TELEMEDICINE AND PRIME-US EDUCATION FACILITIES |
|
$35,000,000.00 |
Ad/Bid |
| |
M8402 |
|
CORRIDOR REPAIR PROJECTS |
|
$1,000,000.00 |
Ad/Bid |
| |
M8402A |
|
MSB CORRIDOR REPAIR PROJECT |
|
$200,000.00 |
Ad/Bid |
| |
M8402B |
|
CSB CORRIDOR REPAIR PROJECT |
|
$200,000.00 |
Ad/Bid |
| |
M8402C |
|
HSIR BUILDINGS ELEVATOR LOBBY AREA REPAIR PROJECT |
|
$200,000.00 |
Ad/Bid |
| |
M8404 |
|
MUW 200 SAA REMODEL AND STAFF RELOCATION |
|
$1,179,424.00 |
Final Documents |
| |
M8425 |
|
MSB 564 CONVERT LAB TO OFFICE SPACES |
|
$535,290.00 |
Ad/Bid |
| |
M9409 |
|
CAMPUS LIBRARY 24 HOUR ACCESS RESTROOMS |
|
$10,520.00 |
Programming |
| |
M9412 |
|
LIBRARY MU WEST EXTERIOR HANDRAIL SAFETY IMPROVEMENTS |
|
$35,000.00 |
Design/Engineer Selection |
| SANDRA BECK |
| |
M1415 |
|
MISSION BAY ART IMPLEMENTATION PROJECT |
|
$1,406,045.00 |
Ongoing |
| |
M4470 |
|
MB BUILDING 17A/B CARDIOVASCULAR RESEARCH BUILDING (CVRB) |
|
$254,000,000.00 |
Construction |
| |
M4470A |
|
PRELIMINARY UTILITY PLANT EXPANSION (PHASE 2 CVRB) |
|
$3,469,092.00 |
Ad/Bid |
| |
M5421 |
|
MISSION BAY CIVIL MASTER PLAN STUDY |
|
$570,350.00 |
Final Documents |
| |
M7419 |
|
MISSION BAY CENTRAL UTILITY PLANT PROGRAMMING STUDY |
|
$1,000,000.00 |
Programming |
| |
M7463 |
|
MISSION BAY 12KV AND IT DUCT BANK ON 13TH STREET (NELSON RISING LANE) |
|
$2,862,706.00 |
Warranty |
| |
M8408 |
|
MISSION BAY 2ND PARCEL INFRASTRUCTURE PHASE 3 |
|
$1,000,000.00 |
Construction |
| |
M8448 |
|
MB 2ND PARCEL CIVIL UTILITIES AND SURFACE IMPROVEMENTS - PHASE 1 (19A) |
|
$2,986,915.00 |
Design Development |
| |
M8449 |
|
MB 2ND PARCEL CUP UTILITIES - PHASE 1 (19A) |
|
$7,000,000.00 |
Design Development |
| SUSAN SIMPSON |
| |
M2444 |
|
MSB IMPROVEMENTS PHASE 2 |
|
$35,355,000.00 |
Construction |
| |
M7445 |
|
MSB IMPROVEMENTS PHASE 3 |
|
$26,200,000.00 |
Programming |
| |
M8401 |
|
MISSION BAY UTILITIES & DISTRIBUTION PHASE 1 LANDSCAPE |
|
$1,178,478.00 |
Construction |
| |
M8416 |
|
GH TEACHING LABORATORY |
|
$300,000.00 |
Construction Documents |
| |
M9402 |
|
MB BYERS HALL 5 NIH GRANT |
|
$50,000.00 |
Programming |
|