Project |
|
Project Name |
|
Project Manager |
|
Phone |
|
Start |
|
End |
|
% Complete |
|
|
 |
| |
|
MISSION BAY UTILITIES |
|
|
 |
| |
|
M4470A |
|
PRELIMINARY UTILITY PLANT EXPANSION (PHASE 2 CVRB) |
|
SANDRA BECK |
|
476-0962 |
|
12/16/09 |
|
|
|
100% |
|
|
| |
|
DESC: |
|
Expansion of PUP equipment to support 17AB project. |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
M8408 |
|
MISSION BAY 2ND PARCEL INFRASTRUCTURE PHASE 3 |
|
SANDRA BECK |
|
476-0962 |
|
04/24/09 |
|
|
|
100% |
|
|
| |
|
DESC: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|