Project |
|
Project Name |
|
Project Manager |
|
Phone |
|
Start |
|
End |
|
% Complete |
|
|
 |
| |
|
MISSION CENTER BUILDING |
|
|
 |
| |
|
M7414A |
|
MCB DEAERATOR (DA) TANK AND PIPING REPLACEMENT |
|
DAN KRASNOW |
|
476-6822 |
|
|
|
|
|
50% |
|
|
| |
|
DESC: |
|
Replace aging deaerator tank and piping. |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
M7416A |
|
MCB FAN AND MOTOR REPLACEMENT |
|
DAN KRASNOW |
|
476-6822 |
|
|
|
|
|
50% |
|
|
| |
|
DESC: |
|
Replace fan motors, add VFD's. Fan, 4-1. 4-2, Demo SF 21- and install fan wall system |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
M7480 |
|
MCB 2ND FLR PEDIATRICS NEUROPATHOLOGY LAB RENOVATION |
|
DON SZETO |
|
476-8071 |
|
07/31/09 |
|
|
|
95% |
|
|
| |
|
DESC: |
|
Update and fume hood installation in existing lab at MCB 234-238. |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
M8403 |
|
MCB 3RD FLOOR OAAIS & STUDENT ACCOUNTS |
|
DON SZETO |
|
476-8071 |
|
09/01/09 |
|
|
|
75% |
|
|
| |
|
DESC: |
|
Occupancy of approx. 7971 ASF for Student Accounts and OAAIS office & support Program at MCB 3rd floor. |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
M8451 |
|
MCB STAIRWELL LIGHT FIXTURE REPLACEMENT |
|
DAN KRASNOW |
|
476-6822 |
|
|
|
|
|
50% |
|
|
| |
|
DESC: |
|
Demolish existing fixtures in stairwells. Install ceiling/wall-mounted Lamar model VO-2-32-E8-U-2C-EM (or equal, no known equal) bi-level stairwell fixtures equipped with integral occupancy sensors. work to be performed in-house |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|